How is the benefits management approach used in the 'closing a project process?
How is the benefits management approach used in the 'closing a project process?
In the 'closing a project' process, the benefits management approach is used to assess any benefits that have already been realized. This is a key activity to ensure that the project can effectively report on what it has achieved during its lifecycle, and to update any records for post-project review and benefits tracking.
20.2 assess any benefits that have already been realized and update the benefits management approach to include any post-project benefit reviews I think it should be A
A is Correct
A is the answer