Which statement is TRUE with regard to technical stages?
Which statement is TRUE with regard to technical stages?
Technical stages often overlap. This is due to the nature of project work where different technical activities may need to be carried out simultaneously rather than sequentially to meet project timelines and dependencies.
Know I'm pretty sure delivery steps = technical stages, thus referring to 9.3.1.1 we see that "Delivery steps often overlap...". Also, all the other are clearly falses.
This is possibly a question from the earlier versions of the exam. No mention is made of 'Technical Stages' in the 2017 Version 6 but the Technical stages correspond to the discussion on Delivery steps in the Plans Chapter ( #9) in the 2017 Version 6
Management stages and delivery approaches - Page 103
A) False - Technical stages can occur sequentially or in parallel. B) False - Technical stages relate to the project lifecycle and work content, not management decision points. C) True - It is common for technical stages to happen concurrently due to dependencies in the work flow. D) False - Technical stages don't define resource/authority commitments - that is done at management stages in PRINCE2.
"D". Ref 9.3.1.1 "Management stages and delivery approaches"