Question 25

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

    Correct Answer: C

    The process triggered towards the end of the final stage when all the assigned work has been completed is 'Closing a Project'. This process involves finalizing and validating that the project has met its objectives and that all deliverables have been completed according to the project plan. It ensures the formal closure of the project and handover of completed products to the relevant stakeholders.

Discussion
peppeOption: C

I believe is C: "received completed work"

FireyOption: C

At the end of the last stage, the Closing a Project process will be invoked and therefore, the Project Manager will start to prepare the project for closure.