Question 19

Which is an objective of the Closing a Project process?

    Correct Answer: B

    An objective of the Closing a Project process is to assess any benefits that have already been realized. This involves reviewing the benefits that have been achieved up to the point of project closure, which is a crucial step in understanding the project's success and impact.

Discussion
JasonbahrOption: B

The objective of the closing a project process is to: - verify user acceptance of the project's products - ensure that the host site is able to support the products when the project is disbanded - review the performance of the project against its baselines - assess any benefits that have already been realized and update the benefits management approach to include any post-project benefit reviews - ensure that provision has been made to address all open issues and risks, with follow-on action recommendations.

a2d1fd1Option: B

B is correct.

peppeOption: B

B is correct "assess any benefits that have already been realized and update the benefits management approach to include any post-project benefit reviews"