PRINCE2-Practitioner Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Exam - Question 281


During stage 3 work on the 'planned pilot courses' is underway. The costs of the 'delivered pilot courses' have been re-estimated as part of this work. The costs are significantly higher than originally estimated.

Who should review how these costs will affect the business case, and why?

Show Answer
Correct Answer: B

Project assurance should review how the increased costs will affect the business case because they are responsible for ensuring that the project continues to meet its objectives and remains viable. They are tasked with assessing the impact of changes on the business case, ensuring that it aligns with the corporate standards and remains justified in terms of cost and benefits.

Discussion

1 comment
Sign in to comment
ravi_awsOption: B
Oct 7, 2023

B. Project assurance, because they should be involved in assessing the impact of changes on the business case