Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 281

During stage 3 work on the 'planned pilot courses' is underway. The costs of the 'delivered pilot courses' have been re-estimated as part of this work. The costs are significantly higher than originally estimated.

Who should review how these costs will affect the business case, and why?

    Correct Answer: B

    Project assurance should review how the increased costs will affect the business case because they are responsible for ensuring that the project continues to meet its objectives and remains viable. They are tasked with assessing the impact of changes on the business case, ensuring that it aligns with the corporate standards and remains justified in terms of cost and benefits.

Discussion
ravi_awsOption: B

B. Project assurance, because they should be involved in assessing the impact of changes on the business case