Question 64

Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

    Correct Answer: C

    The Project Manager indeed has day-to-day control of a management stage within the limits laid down by the Project Board, which is statement 1. Statement 2 is also correct because if a Team Manager forecasts a deviation beyond Work Package tolerances, it should be referred to the Project Manager. Therefore, both statements are true.

Discussion
bcbarmanOption: C

Both 1 and 2 are correct, the PM manages the world within their thresholds, and the same for the team manager. If there is a issues outside of the tolerances, it goes from Team manager to PM, then to exception reports and to the board.