Question 104

The chair of a quality review meeting advised the Team Manager that, because there were so many major issues, the product had been rejected. The presenter estimated that the corrections would take about two weeks. The re-assessment of the product will take a further week, resulting in a three-week delay. The Work

Package only has one week tolerance.

Which 2 actions should the Team Manager take in response to this situation?

    Correct Answer: C, D

    When the Work Package tolerance is forecast to be exceeded, the Team Manager should take immediate action to address this critical situation. Raising an issue explaining that tolerances are forecast to be exceeded is necessary to ensure the Project Manager is aware of the issue and can take appropriate actions to manage it. Furthermore, the Team Manager should advise the Project Manager of the risk that there may be a two-week delay in the delivery of one of the products, allowing for informed decision-making and potential re-planning. These actions are crucial for effective communication and management of project risks and issues.

Discussion
CilubaOptions: CE

CE should be the answers

johnzoidsOptions: CE

i believe the ans to be C and E

PrincessPenguin

CE is written at the end of E. ("E. Ensure that the Quality Register is updated with the quality review result. CE ")

johnzoids

No Answer given