Which of the following is False?
A Successful project management team should.
Which of the following is False?
A Successful project management team should.
A successful project management team should indeed have business, user, and supplier stakeholder representation, ensure appropriate governance by defining responsibilities, and have an effective strategy to manage communication flows. It is false to say that the team should never be reviewed and that members should stay with the team for the duration of the project. It is important to regularly review team composition and effectiveness to ensure the project remains on track and benefits from necessary skills and perspectives.
B is CORRECT (it is the only answer which is false). Answer A is not false, according to 7.1. (beginning of page 60) successful project management team should have all three stakeholders representation :)
Therefore, all three stakeholder interests need to be represented effectively in the project management team; two out of three is not enough
A is correct, see 7.1