Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 7

Which is a type of issue?

    Correct Answer: B

    A request for change is a type of issue. In project management, specifically within the PRINCE2 methodology, an issue is considered to be either a request for change, an off-specification, or a problem/concern. A request for change involves proposing a modification to a baseline and is classified as an issue that needs to be managed.

Discussion
FireyOption: B

According to PRINCE2, an issue can be 1) request for change, 2) an off-specification, or 3) problem/concern.

JasonbahrOption: B

This is correct. Request for change: A proposal for a change to a baseline. It is a type of issue.