When does the ‘directing a project’ process start?
When does the ‘directing a project’ process start?
The 'Directing a Project' process starts after the project has been authorized by the business layer. This is because the process involves the project board providing overall direction and decisions regarding the project after it has been formally authorized to proceed.
"The PRINCE2 Directing a Project process starts when the Starting Up a Project process completes and is triggered by the request from the project manager to initiate a project."