At the end of initiation there is +1 week 1-2 weeks time tolerance for this project. Which statement is true?
At the end of initiation there is +1 week 1-2 weeks time tolerance for this project. Which statement is true?
Additional time tolerance for the project could be found by adding extra resources without affecting other tolerances. This approach allows the project to stay within the existing time constraints by increasing capacity and efficiency. It provides a practical solution to managing time tolerances without compromising the planned stages or team plans. Allocating project-level time tolerance entirely to a single stage or manipulating time tolerance across Team Plans might not be as effective or feasible.
If stage 2 is last stage then option B is true otherwise option C
C. The Stage Plan for stage 2 could create some additional project time tolerance by allowing no time tolerance in Team Plans. This is because the project time tolerance of +1 week / -2 weeks is a buffer for the entire project, not just for one stage. If the Stage Plan for stage 2 does not use any of this tolerance (i.e., it is planned to be completed on time), then the remaining project time tolerance could be used for other stages or unforeseen delays. This would effectively create additional project time tolerance.
Can someone explain this please?
In init stage you can use all of your tolerances.