How many management stages should a PRINCE2 project consist of?
How many management stages should a PRINCE2 project consist of?
A PRINCE2 project should consist of a start-up stage, an initiation stage, and at least one other management stage to cover the remainder of the project. The start-up stage allows for the feasibility of the project to be assessed, the initiation stage is for detailed planning, and the management stages handle the execution and control of the project. Therefore, option A is correct.
C is correct. there should be at least 2 stages within a project.