Question 1

Which of the following statements describes an outcome?

    Correct Answer: C

    An outcome is a measurable improvement that results from a change. It reflects the positive impacts that a project aims to achieve. Therefore, the correct option is 'A measurable improvement resulting from a change.'

Discussion
Alex_28

clearly states in section 6.1

EleftheriiaOption: B

Correct is B, also fro 6.2.3: "The principle of this linkage is straightforward; however, reality is often much more difficult. In order for the benefits to be realized, the outcomes have to be achieved, which means that the outputs from the project actually have to be used and used in the way intended."