Which is created during the Starting up a Project process?
Which is created during the Starting up a Project process?
The Project Mandate is created during the Starting up a Project process. It provides the reasons for the project and defines the business case. This document is crucial to initiate the project and provides the foundation for further planning and approvals.
A. Project mandate: before starting up the project B. Project management team role descriptions: starting up the project C. Communication Management Strategy: initiating the project D. Quality Register: initiating the project
In SU will be appointed the Executive and Project Manager, and this are project management team roles
B is correct
PMT Team role will be defined in IP, not Su in SU, the PMT (high level) will be nominated.