Question 278

The Health and Safety Training Project is a critical project within a programme. Due to resource constraints within the programme, the programme manager has been appointed as both executive and project manager of the Health and Safety Training Project.

Is this an appropriate action, and why?

    Correct Answer: D

    The role of executive and project manager should remain separate for governance reasons. This separation is important to maintain impartiality and ensure that proper checks and balances are in place within the project management structure.

Discussion
kuku1789Option: B

it is B (The programme manager may be the executive for one or more of the projects)

kuku1789

D is correct