PRINCE2-Foundation Exam - Question 13


If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

Show Answer
Correct Answer: C

The Issue Report is the correct document because it includes a detailed description, impact assessment, and recommendations for addressing a request for change, off-specification, or other issues that need formal handling by the Project Board and Project Manager.

Discussion

4 comments
Sign in to comment
JasonbahrOption: C
Apr 11, 2021

issue report: A report containing the description, impact assessment and recommendations for a request for change, offspecification or a problem/concern . It is created only for those issues that need to be handled formally.

peppeOption: C
Oct 15, 2021

correct c

missmanouOption: C
Mar 25, 2022

C is correct

a2d1fd1Option: C
Apr 8, 2024

C is correct, an issue report implies an issue is being dealt with formally.