Question 13

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

    Correct Answer: C

    The Issue Report is the correct document because it includes a detailed description, impact assessment, and recommendations for addressing a request for change, off-specification, or other issues that need formal handling by the Project Board and Project Manager.

Discussion
JasonbahrOption: C

issue report: A report containing the description, impact assessment and recommendations for a request for change, offspecification or a problem/concern . It is created only for those issues that need to be handled formally.

peppeOption: C

correct c

a2d1fd1Option: C

C is correct, an issue report implies an issue is being dealt with formally.

missmanouOption: C

C is correct