PRINCIPLES -
The Health and Safety Training project is following ABC Company's standard course development model. The executive wants start the project as quickly as possible to exploit the market opportunities offered by the new legislation. Therefore, the executive has advised the project manager that a project brief is not required, and that the project can proceed to the initiation stage.
Is this an appropriate action for the 'continued business justification' principle, and why?