Question 163

Which is an objective of the 'starting up a project' process?

    Correct Answer: D

    One of the primary objectives of the 'starting up a project' process is to appoint the project management team. This is crucial for establishing the framework and leadership for the project's successful initiation and execution. Ensuring that a qualified team is in place helps provide clarity and direction for the project's subsequent stages.

Discussion
Prince_GemOption: D

I think the answer is D as A is part of Directing by Project Board ?

TesteurtestOption: D

D is the right answer A. To approve the initiation stage (directing) B. To select the project mandate (before starting up the project and selected by corporate mgmt) C. To define the project quality management approach (initiation) D. To appoint the project management team (starting up)

renzaOption: D

D is the right answer A. To approve the initiation stage (directing) B. To select the project mandate (before starting up the project and selected by corporate mgmt) C. To define the project quality management approach (initiation) D. To appoint the project management team (starting up)

RznNsrOption: D

D is the right answer

lucafrancoOption: D

Corretct answer is D. A. To approve the initiation stage is in DIrecting a project process B. To select the project mandate doesnt have any sense in any process C. To define the project quality management approach is a initiating a process task,

Martin77Option: D

As per Figure 14.1 Overview of starting up a project (Prince2 guide) appoint the executive and project manager is the first step (which are both part of the Project Management team). D seems to be correct here

Steven2021

Sure, but if you look a second time, you'll see that they are only one part of the entire process called "Starting up a project", you see the last output of this process is "Plan the initiation stage", so after this last one so-called "Starting up a project" process is set, the next stage will be started

MehanOption: D

D is correct

LenlenlenOption: D

should be D

ejaymacOption: D

Correct answer is D. A falls under directing a project.

VikceOption: D

agree, correct answer id D.

Risto83Option: D

D 14.2: The objective of the starting up a project process is to ensure that: ● there is a business justification for initiating the project (documented in an outline business case) ● all the necessary authorities exist for initiating the project ● sufficient information is available to define and confirm the scope of the project (in the form of a project brief) ● the various ways the project can be delivered are evaluated and a project approach selected ● individuals are appointed who will undertake the work required in project initiation and/or will take significant project management roles in the project ● the work required for project initiation is planned (documented in a stage plan) ● time is not wasted initiating a project based on unsound assumptions regarding the project’s scope, timescales, acceptance criteria and constraints.

Steven2021Option: A

I would have said A because in chapter 14.1 the very first sentence is this: "The purpose of the starting up a project process is to ensure that the prerequisites for initiating a project* are in place [...]". So *this is an actual stage, therefor I would say A is correct.

peppeOption: D

D is correct

DS001Option: B

A is part of Directing by Project Board so surely cannot be an answer to this question

Wombat1987Option: D

The correct answer is D. https://prince2.wiki/processes/starting-up-a-project/ The following Activities are to be done in the Starting Up a Project process: ... Design and appoint the project management team. ...