PRINCE2-Foundation Exam - Question 149


What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?

Show Answer
Correct Answer: C

To meet the minimum requirements for applying the business case theme in benefits management, it is essential to document the management actions needed to ensure benefits are realized. This includes defining the specific actions that will be put in place to guarantee that the project's outcomes are achieved and the benefits materialize. This approach ensures a structured plan to track, manage, and verify the realization of benefits throughout the project lifecycle.

Discussion

13 comments
Sign in to comment
peppeOption: C
Oct 17, 2021

C is correct pg 48

PanzerknackerOption: C
Nov 9, 2020

Agree, C is supposed to be correct.The senior users responsibility is not explicitly mentioned in the minimum requirements

Martin77Option: C
Apr 14, 2021

C is correct . Reference - Prince2 manual, 6.2 (Business case theme chapter)

renzaOption: C
Feb 26, 2023

c is the correct answer

SGN63Option: C
Mar 11, 2023

answer C

GetRaj
Jul 7, 2020

Both option A and C seems to be correct.

GetRaj
Aug 20, 2020

Prince 2 Manual Section 6.2 Benefits Management approach: Defines the management actions that will be put in place to ensure that the project's outcomes are achieved and confirm that the project's benefits are realized. Hence C is correct

MehanOption: C
Jan 14, 2021

only C is correct, appointing the senior user is not explicitly stated. so C is the most correct answer. Ref.6.2

Steven2021
Nov 30, 2021

Under 6.1 it is clearly written that the senior user is responsible for for that, and that the executive needs to make sure that the decision of the senior user regarding benefits will have value for money in the project

Wombat1987Option: C
Mar 31, 2021

The correct answer is C. https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes Minimum requirements Your project must create and maintain a business justification (in the form of a business case), and you should review and update it throughout your project. You must define management actions to ensure the expected outcomes are achieved and the benefits are realized. You must define and document the roles and responsibilities for the business case and the management of benefits. Finally, you must produce and maintain a benefits management approach.

Steven2021Option: A
Nov 30, 2021

A is correct, page 47, chapter 6.1 "The senior user is responsible for specifying the bnefits and subsequently realizing the benefits through the use of the products provided by the project. The eexcutive is responsible for ensuring that those benefits specified by the senior user represent value for money, are aligned with corporate, programe management or customer objectives, and can be realized"

Risto83Option: C
Dec 24, 2022

C 6.2: Benefits management approach Defines the management actions that will be put in place to ensure that the project’s outcomes are achieved and confirm that the project’s benefits are realized.

TesteurtestOption: A
Aug 22, 2023

The Senior User is responsible for specifying the benefits and realizing the benefits. https://prince2.wiki/theme/business-case/

Haranp12Option: C
Nov 10, 2023

Both A and C are correct. Define and document the roles and responsibilities for the business case and benefits management is clearly mentioned in the book and thats why i think it is a better answer. In the book, it mentions define the management actions that will be put in place to ensure that the project’s outcomes are achieved and confirm that the project’s benefits are realized. This looks like option C but maybe this statement means defining actions that will be put in place to ensure project outcomes are achieved and project benefits are to be confirmed somehow

tarikaygulOption: C
Dec 21, 2023

c is the correct answer Benefits management Approach • Defines the benefits management actions and benefits reviews that will be put in place ◦To ensure that the project’s outcomes are achieved ◦Confirm that the project’s benefits are realized