What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?
What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?
To meet the minimum requirements for applying the business case theme in benefits management, it is essential to document the management actions needed to ensure benefits are realized. This includes defining the specific actions that will be put in place to guarantee that the project's outcomes are achieved and the benefits materialize. This approach ensures a structured plan to track, manage, and verify the realization of benefits throughout the project lifecycle.
C is correct pg 48
answer C
c is the correct answer
C is correct . Reference - Prince2 manual, 6.2 (Business case theme chapter)
Agree, C is supposed to be correct.The senior users responsibility is not explicitly mentioned in the minimum requirements
c is the correct answer Benefits management Approach • Defines the benefits management actions and benefits reviews that will be put in place ◦To ensure that the project’s outcomes are achieved ◦Confirm that the project’s benefits are realized
Both A and C are correct. Define and document the roles and responsibilities for the business case and benefits management is clearly mentioned in the book and thats why i think it is a better answer. In the book, it mentions define the management actions that will be put in place to ensure that the project’s outcomes are achieved and confirm that the project’s benefits are realized. This looks like option C but maybe this statement means defining actions that will be put in place to ensure project outcomes are achieved and project benefits are to be confirmed somehow
The Senior User is responsible for specifying the benefits and realizing the benefits. https://prince2.wiki/theme/business-case/
C 6.2: Benefits management approach Defines the management actions that will be put in place to ensure that the project’s outcomes are achieved and confirm that the project’s benefits are realized.
A is correct, page 47, chapter 6.1 "The senior user is responsible for specifying the bnefits and subsequently realizing the benefits through the use of the products provided by the project. The eexcutive is responsible for ensuring that those benefits specified by the senior user represent value for money, are aligned with corporate, programe management or customer objectives, and can be realized"
The correct answer is C. https://www.knowledgetrain.co.uk/project-management/prince2/prince2-themes Minimum requirements Your project must create and maintain a business justification (in the form of a business case), and you should review and update it throughout your project. You must define management actions to ensure the expected outcomes are achieved and the benefits are realized. You must define and document the roles and responsibilities for the business case and the management of benefits. Finally, you must produce and maintain a benefits management approach.
only C is correct, appointing the senior user is not explicitly stated. so C is the most correct answer. Ref.6.2
Under 6.1 it is clearly written that the senior user is responsible for for that, and that the executive needs to make sure that the decision of the senior user regarding benefits will have value for money in the project
Both option A and C seems to be correct.
Prince 2 Manual Section 6.2 Benefits Management approach: Defines the management actions that will be put in place to ensure that the project's outcomes are achieved and confirm that the project's benefits are realized. Hence C is correct