Where should decisions regarding the tailoring of the project be recorded?
Where should decisions regarding the tailoring of the project be recorded?
Decisions regarding the tailoring of the project should be recorded in the Project Initiation Documentation (PID). The PID provides a baseline for the project, setting out the project's objectives, scope, and structure, and it is the appropriate place to record such decisions to ensure all stakeholders are aligned and aware of how the project will be tailored to meet its specific needs.
Yes. In the PID. Quite a bit of these answers are wrong
Tailoring Section appears in PID
it should be in PID
In the PID
b ic correct
Correct answer is B. In the Project Initiation Documentation
the correct answer is PID