Which is a purpose of the Closing a Project process?
Which is a purpose of the Closing a Project process?
The purpose of the Closing a Project process is to provide a fixed point at which acceptance of the project’s product is confirmed, and to recognize whether the objectives set out in the original Project Initiation Documentation (PID) have been achieved. This ensures that the project has met its goals or that any necessary approved changes have been successfully implemented. Option A, which refers to authorizing the final stage, and Option D, which involves delegating day-to-day management, do not relate to the closure of the project but rather to ongoing project activities. Option B is incorrect because the closing process does not confirm that all benefits have been achieved; rather, it ensures that the project deliverables are complete and meet the required standards.
The purpose of the closing a project process is to provide a fixed point at which acceptance of the project's product is confirmed, and to recognize that objectives set out in the original PID have been achieved (or approved changes to the objectives have been achieved), or that the project has nothing more to contribute.
Thanks Jasonbahr, you have been very helpful
C is correct "The purpose of the closing a project process is to provide a fixed point at which acceptance of the project’s product is confirmed, and to recognize that objectives set out in the original PID have been achieved