Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 117

Which should be provided by corporate or programme management before the Starting up a Project process commences?

    Correct Answer: D

    Before the Starting up a Project process commences, corporate or programme management must provide authority to initiate a project. This is a fundamental precondition as it legitimizes the project and ensures that necessary resources and support will be available. Without this authority, the project cannot be formally initiated.

Discussion
lucafrancoOption: B

14.3 The project mandate should provide the terms of reference for the project and should contain sufficient information to identify at least the prospective executive of the project board