Question 40

In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator:

    Correct Answer: B

    In the PRINCE2 methodology, the role of administrator in the Quality review technique is typically carried out by Project Support. This is because Project Support is responsible for providing administrative services to the project, including maintaining documentation, configurations, and ensuring that procedures are followed correctly. The Project Manager and Team Manager have different responsibilities focused more on overseeing and executing the project, while Project Assurance is more concerned with ensuring the project's alignment with business objectives and quality controls.

Discussion
ManikRoyOption: B

Page 83, Project Support responsibilities.

georgio1974Option: B

i would agree that it is B but it is not clear from any point that project support should provide administration support on pages 90-92 in new edition 2023

PieroBeOption: B

Project Support, refer to 8.4.3.

mattersOption: B

Refer to the Project Support responsibilities in Table 8.1 of the manual