Question 247

Which stakeholder interest does the senior supplier represent?

    Correct Answer: B

    The senior supplier represents the interests of those providing administrative services and advice during the project. In PRINCE2, the senior supplier role is responsible for ensuring that the supplier resources required for the project are provided, and that the projects deliverables are produced to the required standard. This involves offering expertise, managing relationships with suppliers, and ensuring that the project stays aligned with technical and quality standards. Their focus is on the delivery phase rather than post-project maintenance or support.

Discussion
fgtfgtet4r56yOption: D

D. Those providing maintenance and support services after project closure The senior supplier in PRINCE2 represents the stakeholder interest of those who will provide maintenance and support services after the project closure. They are responsible for ensuring that the project's products are maintainable and can be effectively supported in the post-project operational phase. Their focus is on the long-term viability and supportability of the project's outputs.