Which of the following is NOT a trigger for the project manager to authorize a work package?
Which of the following is NOT a trigger for the project manager to authorize a work package?
Reporting highlights is not a trigger for the project manager to authorize a work package. A work package is typically authorized based on key project activities like stage authorization, corrective actions being implemented, or an exception plan being approved. Reporting highlights involve regular updates on project progress and do not have direct influence over the authorization of specific work packages.
B - corrective action
B Corrective action is not a trigger for the project manager to authorize a work package. Corrective action is taken when there is a deviation from the plan or when a problem arises that needs to be addressed