Question 190

Which principle helps to ensure that all changes to the outputs are agreed?

    Correct Answer: B

    The principle of 'Focus on products' in PRINCE2 helps ensure that all changes to the project's outputs are agreed upon. This principle emphasizes the importance of clearly defining and understanding the project's products (deliverables) and their quality criteria. When changes are proposed, they need to align with the agreed-upon product descriptions and quality requirements, ensuring that changes are properly assessed and agreed upon.

Discussion
ConstanzaOption: B

B is correct, p.26/3.6

KopytinaNOption: B

B is correct

fgtfgtet4r56yOption: B

B. Focus on products The principle of "Focus on products" in PRINCE2 helps ensure that all changes to the project's outputs (products) are agreed upon. It emphasizes the importance of clearly defining and understanding the project's products (deliverables) and their quality criteria. When changes are proposed, they need to align with the agreed-upon product descriptions and quality requirements, and this principle helps ensure that changes are properly assessed and agreed upon.

lferolmOption: B

B is correct