Question 165

ABC Company produces a corporate business plan which includes the targets for the next 12 months. For the Health and Safety Training Project, a feasibility study was carried out and, as a result, the expected sales were included in this plan. During the 'starting up a project' process, the executive advised the project manager that the corporate business plan provides sufficient justification to initiate the project.

Is this a correct application of the 'continued business justification' principle, and why?

    Correct Answer: B

    The correct application of the 'continued business justification' principle involves ensuring that the business justification is documented and approved. The corporate business plan, having undergone a feasibility study and been included after validation, provides a form of this recorded justification. This aligns with the principle's requirement that there must be a documented and approved justification for initiating the project, which must be maintained throughout its life. Therefore, the approval of the corporate business plan fulfills this requirement.

Discussion
mogasserOption: B

I believe it's B, based on 3.1 page 21

MortenCOption: B

3.1 page 21

ManikRoyOption: B

Agree with others in the comment section that B seems to be the most appropiate of all options.

ravi_awsOption: B

A is incorrect because the executive alone can't justify the project. C is incorrect because other documents can provide the justification. D is incorrect because some form of justification is required for startup. Therefore, B is the best answer. The corporate plan's approval fulfills the need for documented justification according to the principle.

CarpediempyyOption: A

When I read this I thought it was B "In most organizations the business justification is usually documented in some form of business case. " but Its A, bcs of this, PRINCE2 requires that for all projects: •there is a justifiable reason for starting the project •that justification is recorded and approved •the justification remains valid, and is revalidated, throughout the life of the project.

MortenC

Check 7.2.1.10

MortenC

wrong reference...please delete

ameyaenggOption: C

Correct Answer : C

ameyaengg

Sorry TYPO : correct answer is B