The project is approaching the end of stage 3, and stage 4 is being planned as part of the 'managing a stage boundary' process.
Which action should the project manager carry out as part of the 'update the project plan' activity?
The project is approaching the end of stage 3, and stage 4 is being planned as part of the 'managing a stage boundary' process.
Which action should the project manager carry out as part of the 'update the project plan' activity?
The project manager should include the actual time and cost of the work to prepare the 'marketing materials' in the project plan. This is part of tracking and updating the project plan to reflect actual performance and incurred costs, which ensures the plan remains accurate and up-to-date as the project progresses.
We need to add actuals (costs and progresses) inherited from closing stage in the project plan.
I think A is correct (19.4.2. and A.16.2)
I would vote for C because it is mentioned in 19.4.3 to update the risk register in the BC.