Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 209

Which product should show that the project has been closed prematurely and has not achieved the objectives defined in the Project Initiation Documentation

(PID)?

    Correct Answer: B

    The End Project Report is designed to provide a summary of the project's performance against its original objectives, benefits, costs, and tolerances. If a project is closed prematurely, this report would document the reasons for the closure and indicate to what extent the project objectives were achieved or not achieved. This makes it the appropriate product to show that the project has been closed prematurely and has not met the objectives defined in the Project Initiation Documentation.

Discussion
ravi_awsOption: B

B an Exception Report is used to document issues that are causing a project to veer off track1. It’s typically produced when a stage plan or project plan is forecast to exceed tolerance levels set2. However, the Exception Report is more about identifying the issue and offering options and recommendations for how to proceed2. On the other hand, the End Project Report provides a summary of how the project performed against its original objectives, benefits, costs, and tolerances3. If a project is closed prematurely, this report should show the reasons for the closure and the extent to which the project objectives were met or not met

GSD547Option: B

B is correct answer, End Project Report Composition (Lessons) states 'if project was prematurely closed, then reasons should be explained'. (p302)

CilubaOption: C

Problem with B option is, when the end project report is created, the project closure hasn't been approved.