Which statement is an appropriate entry for the outline Business Case heading within the Project Brief?
Which statement is an appropriate entry for the outline Business Case heading within the Project Brief?
An appropriate entry for the outline Business Case heading within the Project Brief should cover why the project is needed and the business options selected, along with their likely costs and benefits. Option B, which states that 'External consultants were employed to conduct a feasibility study to identify the options, their likely costs and benefits,' meets this requirement. Hence, it is the correct answer.
I think option B is the correct answer. Refer A.19.2 Outline business case :- Reasons why the project is needed and the business option selected. This will later be developed into a detailed business case during the initiating a project process
I think it is B, see ref. A.19.2. Overall project cost and time are (detailed) BC contents.
Or is it more the statement that "external contractors" were selected as a Business Option?
The Outline Business Case should cover the reasons why the project is needed and the business option selected. So I also think B, as the feasibility study would include this information?
I feel the ans need to be B. ref: A19.2
B. External consultants were employed to conduct a feasibility study to identify the options, their likely costs and benefits. The outline Business Case is a document that provides a high-level view of the project and outlines the expected costs, benefits, and risks associated with the project 1 . It is an important document that helps to ensure that the project is feasible and that the business case is sound. An appropriate entry for the outline Business Case heading within the Project Brief in PRINCE2 is one that outlines the benefits of what is being recommended and provides options to solve the business problem