Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 63

When examining a project issue, which three aspects should be considered?

1. Performance targets

2. Business Case

3. Resources

4. Risk

    Correct Answer: D

    When examining a project issue, the focus should be on aspects that are currently affecting the project. Performance targets are crucial as they help measure the project's success. The business case is essential because it justifies the project's existence and continuation. Resources are important since they directly impact project delivery. Risk, on the other hand, typically refers to potential future uncertainties and may not be directly relevant to issues that have already occurred.

Discussion
pollonOption: C

Answer C is correct, see pg 144 of the manual - Impact analysis of an issue should consider: project performance targets, business case, dependent products produced by project, project risk profile

ravi_awsOption: C

C When examining a project issue in PRINCE2, the three aspects that should be considered are: Business Case Risk Performance targets

SantiagoAregentinaOption: C

Ref 11.4.2

WikiVicksOption: D

Incorrect answer. An issue is when something has already occurred. Risk is something that hasn't occurred yet and might occur ( not certain). So C cannot be correct. More likely D is correct