PRINCE2-Foundation Exam - Question 182


According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?

Show Answer
Correct Answer: B

According to the 'defined roles and responsibilities' principle in project management, the project management team must represent directing, managing, and delivering levels. This ensures that there are distinct responsibilities for guiding the project, managing day-to-day activities, and delivering the project's outputs. These roles are essential for a clear and effective project management structure.

Discussion

8 comments
Sign in to comment
PetzaOption: C
Aug 28, 2020

C is the right answer according to PRINCE2 section 3.3 Defined roles and responsibilities

lucafrancoOption: B
Dec 28, 2021

Correct anwer should be B. A is wrong : delivery level is not rappresented in this answer. could be if team manager role was combined with project manager role but here is not indicated. C is wrong: this is project board composition not management team composition D is wrong: Corporate, programme management are outside project management team Moreover figure 7.2 of chapter 7 show the diagram of the project management team as Directing(project board) managing (project manager) and delivering (team manager).

KianaOption: B
Jul 2, 2020

It should be B not C

asalimOption: C
Aug 5, 2020

C is correct

sohrabianiOption: C
Oct 7, 2020

C is correct answer

theotenisOption: A
May 11, 2021

The correct answer should be A, according to the PRINCE2 manual glossary information: project management team = The entire management structure of the project board, and the project manager, plus any team manager, project assurance and project support roles

AC_DoraOption: C
Mar 23, 2024

Ans should be C. According to PRINCE2, a project has 3 primary stakeholders. They are the Business sponsors, Users and Suppliers. Business sponsors are those who make sure the project delivers value for money. Users will use the products once created, so they receive the benefits. Suppliers provide the resources and expertise to the project and produce the products. This principle states that these three primary stakeholders must be correctly represented in the Project Management Team and in the Project Board.

Wombat1987Option: C
Apr 1, 2021

C is the correct one. https://prince2.wiki/principles/defined-roles-and-responsibilities/ PRINCE2 states that a project should have defined and agreed roles and responsibilities within an organization structure that engages the Business, User and Supplier Stakeholder interests.