Question 43

What process aims to ensure accurate progress information is provided to the Project Manager?

    Correct Answer: B

    The process 'Managing a Stage Boundary' aims to ensure accurate progress information is provided to the Project Manager. This process involves assessing the current stage performance, planning the next stage, and ensuring that the project remains viable. Therefore, it is specifically designed to provide accurate and comprehensive progress information to the Project Manager.

Discussion
mattersOption: C

C is correct. Refer to 18.2 Objective #4