Which 2 alternative actions apply to the proposed supplier assurance for this project?
Which 2 alternative actions apply to the proposed supplier assurance for this project?
Considering the proposed supplier assurance for the project, it’s important to have advice on potential changes and their impact on the project’s products, so adding 'Outcome Account Manager' is a valid action. Additionally, removing an individual who is involved with the project to maintain independence is crucial for unbiased assurance.
B AND E