PRINCE2-Practitioner Exam - Question 314


Which 2 alternative actions apply to the proposed supplier assurance for this project?

Show Answer
Correct Answer: DE

Considering the proposed supplier assurance for the project, it’s important to have advice on potential changes and their impact on the project’s products, so adding 'Outcome Account Manager' is a valid action. Additionally, removing an individual who is involved with the project to maintain independence is crucial for unbiased assurance.

Discussion

1 comment
Sign in to comment
ravi_aws
Oct 8, 2023

B AND E