PRINCE2-Practitioner Exam - Question 264


MANAGING A STAGE BOUNDARY -

At the end of stage 3, the pilot courses have been planned and this work revealed that sales of the health and safety training course were expected to be higher than originally expected. Therefore, the project manager revised the sales forecast for the course. This revised forecast needs to be both reviewed and approved.

Who should review this forecast after it has been updated as part of the 'update the business case' activity?

Show Answer
Correct Answer: B

The revised sales forecast should be reviewed by the Business Development Director who is the executive. The executive is responsible for the business case and ensuring that the project remains viable and aligned with the organization's strategic objectives. This role assures that the updated forecast is realistic and will provide the expected benefits to the organization.

Discussion

2 comments
Sign in to comment
kuku1789Option: B
Oct 20, 2022

it is B

ravi_awsOption: B
Oct 7, 2023

The Business Development Director who is the executive