Question 60

In which strategy would the change control process be recorded?

    Correct Answer: B

    The change control process involves managing changes to the project deliverables and ensuring that changes are systematically controlled. This is typically documented in the Configuration Management Strategy, which outlines how configuration items (such as project documents and deliverables) are controlled, tracked, and managed. The Configuration Management Strategy ensures that any changes are identified, recorded, and tracked throughout the project lifecycle.

Discussion
WikiVicksOption: B

Configuration Management Strategy seems to be the in the older version of PRINCE2. In 2017 , Edition 6 this is called Change Control Approach.

ManikRoy

This question is now invalid as per new syllabus as all strategies have been replaced by approaches.

georgio1974Option: D

FIGURE 16.6 PAGE 204