Question 73

DRAG DROP -

PROGRESS -

Here are three statements relating to controlling the progress of the project.

In which management product (A-E) should each statement be recorded?

Choose only one product for each statement. Each product can be used once, more than once, or not at all.

Select and Place:

    Correct Answer:

Discussion
PieroBe

To my opinion: 1 is Highlight report - PM reports a summary of issues currently in the stage 2 is End Project Report - see ref A.8.2 3 is Exception Report - Tolerance has been overcome

Passionaire

* 2. Should be End Stage report. Work packages are under question not the project as a whole.

ravi_aws

In PRINCE2, when you need to address a situation where a project cannot be completed within the time tolerance and you want to consider options like instructing the team manager to work overtime, you would typically capture this in the "Exception Report."

CameronSN

could someone please advise, how to I interpret the answers provided