PRINCE2-Practitioner Exam QuestionsBrowse all questions from this exam

PRINCE2-Practitioner Exam - Question 73


DRAG DROP -

PROGRESS -

Here are three statements relating to controlling the progress of the project.

In which management product (A-E) should each statement be recorded?

Choose only one product for each statement. Each product can be used once, more than once, or not at all.

Select and Place:

Show Answer
Correct Answer:

Discussion

3 comments
Sign in to comment
PieroBe
Jul 25, 2023

To my opinion: 1 is Highlight report - PM reports a summary of issues currently in the stage 2 is End Project Report - see ref A.8.2 3 is Exception Report - Tolerance has been overcome

Passionaire
Jun 8, 2024

* 2. Should be End Stage report. Work packages are under question not the project as a whole.

CameronSN
Mar 23, 2023

could someone please advise, how to I interpret the answers provided

ravi_aws
Oct 1, 2023

In PRINCE2, when you need to address a situation where a project cannot be completed within the time tolerance and you want to consider options like instructing the team manager to work overtime, you would typically capture this in the "Exception Report."