Question 60

Which does NOT reflect the PRINCE2 principle of continued business justification?

    Correct Answer: C

    PRINCE2 principle of continued business justification means that a project should only continue as long as it remains justified. The principle does not imply that only financial benefits justify a project; there can be other types of benefits such as strategic, reputational, or regulatory. Option C specifically mentions stopping a project if it no longer delivers a financial benefit, which does not align with PRINCE2’s broader view of benefits. Therefore, option C does not reflect the principle of continued business justification correctly.

Discussion
peppeOption: C

C is correct

Wombat1987Option: C

C is correct since a project can bring other than financial benefits.

MrMayOption: C

C is correct. The benefit of a project doesn’t have to be financial.

King_LapsOption: C

the correct answer is C

MehanOption: B

I think B is correct.

peppe

wrong! pg 21!