PRINCE2-Foundation Exam - Question 60


Which does NOT reflect the PRINCE2 principle of continued business justification?

Show Answer
Correct Answer: C

PRINCE2 principle of continued business justification means that a project should only continue as long as it remains justified. The principle does not imply that only financial benefits justify a project; there can be other types of benefits such as strategic, reputational, or regulatory. Option C specifically mentions stopping a project if it no longer delivers a financial benefit, which does not align with PRINCE2’s broader view of benefits. Therefore, option C does not reflect the principle of continued business justification correctly.

Discussion

5 comments
Sign in to comment
Wombat1987Option: C
Mar 22, 2021

C is correct since a project can bring other than financial benefits.

peppeOption: C
Oct 19, 2021

C is correct

MehanOption: B
Jan 13, 2021

I think B is correct.

peppe
Oct 19, 2021

wrong! pg 21!

King_LapsOption: C
Oct 1, 2022

the correct answer is C

MrMayOption: C
Feb 8, 2024

C is correct. The benefit of a project doesn’t have to be financial.