PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 69


Whose approval is needed to replace a Stage Plan with an Exception Plan?

Show Answer
Correct Answer: B

The approval needed to replace a Stage Plan with an Exception Plan is the Project Board's. The Project Board is responsible for overseeing project progress and making decisions regarding significant deviations from the plan, which includes approving Exception Plans when tolerances are forecast to be exceeded.

Discussion

1 comment
Sign in to comment
omandeOption: B
Oct 21, 2023

C.1: During the project, the project board should approve exception plans when management-stage-level tolerances are forecast to be exceeded.