Whose approval is needed to replace a Stage Plan with an Exception Plan?
Whose approval is needed to replace a Stage Plan with an Exception Plan?
The approval needed to replace a Stage Plan with an Exception Plan is the Project Board's. The Project Board is responsible for overseeing project progress and making decisions regarding significant deviations from the plan, which includes approving Exception Plans when tolerances are forecast to be exceeded.
C.1: During the project, the project board should approve exception plans when management-stage-level tolerances are forecast to be exceeded.