Question 76

Who is responsible for appointing the Project Manager?

    Correct Answer: B

    The Project Board is responsible for appointing the Project Manager. In the structure of project governance, it is typical for the Project Board to oversee the appointment of key roles, including the Project Manager, to ensure that the project is aligned with the organization's strategic objectives and that there is proper oversight throughout the project's lifecycle.

Discussion
SantiagoAregentinaOption: C

"C". ref C.2.1 "Executive responsibilities"

PieroBeOption: C

ref 14.4.1

ravi_awsOption: B

B Based on the search results, the true statement with regard to the responsibility for appointing the Project Manager in PRINCE2 is: Statement B is True: The Project Board is responsible for appointing the Project Manager.

ManikRoy

This is not correct. It is the Executive responsibilities.