The 'e-learning course' is being delivered by an external consultancy. The team manager has advised the project manager that their plan is confidential and will be displayed on their team board as a list of requirements. The project manager has requested that the team manager share a milestone plan with the project management team instead for them to view.
Is this an appropriate action, and why?