Question 18

What takes place during the Closing a Project process?

    Correct Answer: B

    During the Closing a Project process, ownership of the project's products is transferred to the customer. This transfer signifies the end of the project and the handover of responsibility from the project management team to the customer. This ensures that the project’s deliverables are formally accepted and the project can be officially closed.

Discussion
Martin77Option: B

B is correct here: transfers ownership of the products to the customer and terminates the responsibility of the project management team. reference prince2 - 20.3

plechatOption: B

B is the right answer

peppeOption: B

B is correct " transfers ownership of the products to the customer and terminates the responsibility of the project management team.

Jasonbahr

The project's products must be passed to an operational and maintenance environment prior to the project being closed. This may happen as a single release at the end of the project, or the project approach may include phased delivery where products are handed over in a number of releases.