During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
During the Managing a Stage Boundary process in PRINCE2 methodology, the Project Plan is updated with the estimated costs and time for the stage that is about to begin. The Project Plan encompasses the high-level overview of the entire project, ensuring that each stage is accounted for in terms of resources and time.
During the Managing a Stage Boundary process in PRINCE2 project management methodology, the product that is updated with estimated costs and time for the stage that is about to begin is the Project Plan.