Exam PRINCE2-Foundation All QuestionsBrowse all questions from this exam
Question 111

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

    Correct Answer: D

    During the Managing a Stage Boundary process in PRINCE2 methodology, the Project Plan is updated with the estimated costs and time for the stage that is about to begin. The Project Plan encompasses the high-level overview of the entire project, ensuring that each stage is accounted for in terms of resources and time.

Discussion
FireyOption: D

During the Managing a Stage Boundary process in PRINCE2 project management methodology, the product that is updated with estimated costs and time for the stage that is about to begin is the Project Plan.