Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 97

When does Directing a Project begin?

    Correct Answer: C

    The 'Directing a Project' process begins from the completion of 'Starting up a Project.' The 'Starting up a Project' process ensures that all the prerequisites for project initiation are met, such as appointing a project manager and defining the project approach. Once these steps are completed and the project is authorized to proceed, the 'Directing a Project' process can begin.

Discussion
ravi_awsOption: C

The "Starting up a Project" process is focused on ensuring that the prerequisites for initiating a project are in place, such as appointing the project manager, defining the project approach, and creating the Project Brief. Once this process is successfully completed and the project is authorized to proceed, the "Directing a Project" process begins.