Question 222

Which is an objective of the 'controlling a stage' process?

    Correct Answer: B

    One of the objectives of the 'controlling a stage' process in PRINCE2 is to monitor and control the stage by comparing actual progress against the stage plan and ensuring that the stage remains within tolerance. If deviations from the plan are identified and it becomes necessary to adjust, the process includes replanning the current stage when directed to keep the project aligned with its objectives.

Discussion
robyOption: A

that would be an activity in the Controlling a stage but not an objective. Answer should be A as per below link https://prince2.wiki/processes/controlling-a-stage/#:~:text=The%20purpose%20of%20the%20Controlling,the%20stage%20remains%20within%20tolerance.

fgtfgtet4r56yOption: B

B. To replan the current stage when directed One of the objectives of the 'controlling a stage' process in PRINCE2 is to replan the current stage when directed. This means that if, during the monitoring and control of a stage, it becomes necessary to adjust the stage plan due to deviations or changes in circumstances, the process allows for the creation of an updated plan for the current stage as directed by the project board or other relevant authority. This helps to keep the project on track and aligned with its objectives.

MyName_Option: C

As per the 6th addition pocket guide, one of the Objectives mentioned is - The management stage's products ared delivered within agreed tolerances and they support the achievement of the defined benefits. Hence I thing the correct answer is Option C