Which role can act as the change authority?
Which role can act as the change authority?
The role of project assurance can indeed act as the change authority according to the PRINCE2 guidelines. The project manager or individuals with delegated project assurance responsibilities may assume this role, ensuring changes are authorized and managed properly within the project framework.
Correct answer is A. See section "7.2.1.6 Change Authority" from PRINCE2 manual: "The project manager and/or the people with delegated project assurance responsibilities may act as the change authority. Refer to Chapter 11 for more information on change."
I agree, A is correct