Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 94

During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered.

What should project assurance do next?

    Correct Answer: B

    When the team manager reports that the work to update the 'corporate quality procedures' has been completed, the next step for project assurance should be to check the work package and follow the procedure to deliver completed products. This ensures that the products meet the required quality standards and that the correct processes are followed for delivering the completed products.

Discussion
suneeOption: C

c is correct

anti8

18.4.3

ravi_awsOption: C

In PRINCE2, the role of project assurance includes ensuring that the products produced by the work packages are of the required quality and meet the defined criteria for approval. Therefore, when the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered, the project assurance should verify that all the products to be delivered by the work package have been reviewed and approved before they are formally accepted and used in the project.

lovelifeysl_2021Option: C

I THINK IT IS C