PRINCE2-Practitioner Exam - Question 276


DRAG DROP -

RISK -

The following risk has been identified during a risk identification workshop:

"Because the project is reliant on the government agency accrediting the 'classroom-based training materials' before work can continue on the project, there is a risk that the accreditation will either be withheld or delayed, leading to a delay in the overall project with associated cost implications."

Here are three items of information that will be included in the risk register about this risk.

Under which heading (A-F) should they be recorded?

Choose only ONE heading for each item of information. Each heading can be used once, more than once, or not at all.

Select and Place:

Show Answer
Correct Answer:

Discussion

1 comment
Sign in to comment
ravi_aws
Oct 7, 2023

Risk Risponse, Risk Owner, Proximity