PRINCE2-Foundation Exam QuestionsBrowse all questions from this exam

PRINCE2-Foundation Exam - Question 45


Which process covers the work done by external suppliers who may NOT be using PRINCE2?

Show Answer
Correct Answer: C

The process 'Managing Product Delivery' covers the work done by external suppliers who may not be using PRINCE2. This process ensures that products are created and delivered to the agreed standards and criteria, regardless of the project management method used by the suppliers.

Discussion

2 comments
Sign in to comment
peppe
Oct 16, 2024

C is correct

rahuludayabhanuOption: C
May 5, 2025

C. Managing Product Delivery This process covers the work done by external suppliers or teams, including those who may not be using PRINCE2, as it focuses on managing the delivery of products or work packages.