Exam PRINCE2-Practitioner All QuestionsBrowse all questions from this exam
Question 232

DRAG DROP -

PROGRESS -

The delivery of the 'marketed courses' is expected to be one week late, which will be outside the agreed tolerance for the work package.

Here are three actions relating to the 'progress' theme for this late delivery.

Which role (A-F) is responsible for each action?

Choose only ONE role for each action. Each role may be used once, more than once, or not at all.

Select and Place:

    Correct Answer:

Discussion
ravi_aws

Project assurance to confirm and assure, Project support, Team manager

MortenC

Executive is probably not correct. Project Assurans according to table 12.2