PRINCE2-Practitioner Exam - Question 232


DRAG DROP -

PROGRESS -

The delivery of the 'marketed courses' is expected to be one week late, which will be outside the agreed tolerance for the work package.

Here are three actions relating to the 'progress' theme for this late delivery.

Which role (A-F) is responsible for each action?

Choose only ONE role for each action. Each role may be used once, more than once, or not at all.

Select and Place:

Show Answer
Correct Answer:

Discussion

2 comments
Sign in to comment
MortenC
Feb 11, 2023

Executive is probably not correct. Project Assurans according to table 12.2

ravi_aws
Oct 6, 2023

Project assurance to confirm and assure, Project support, Team manager